Nutanix Prism Central pc.2024.3 End of Life: December 31, 2026

By Scott Bissett  ·  Published: November 25, 2026  ·  Reference guide  ·  Dates read on November 25, 2026 at the Prism Central table of Nutanix's End of Support Life Information page (portal.nutanix.com) and Nutanix's Support Policies and FAQs page (nutanix.com).

Nutanix Prism Central pc.2024.3 reaches End of Support Life on December 31, 2026. Its End of Maintenance date was March 31, 2026. Both dates come from Nutanix's own End of Support Life Information table for Prism Central. The table prints each date as a month, and its notes say the months "refer to the end of the month". The first date has passed: since then, Nutanix's policy gives the pc.2024.3 Upgrade family troubleshooting only, not maintenance releases. The second date is the point where support for pc.2024.3 ends altogether. Two Prism Central lines are inside their maintenance period on the same table: pc.7.5 and pc.7.6.

Quick answer: Nutanix Prism Central pc.2024.3 reaches End of Support Life on December 31, 2026, per Nutanix's End of Support Life Information table. Maintenance ended on March 31, 2026; Nutanix has provided troubleshooting only since then. The upgrade targets are pc.7.5 and pc.7.6. Live status and the EOL Risk Score are on the pc.2024.3 page.

Nutanix's Prism Central policy, in Nutanix's words

Nutanix publishes the rule for Prism Central in section 2.2 of its End of Support Life (EOSL) policy. It reads: "Each Upgrade family is Maintained for a fifteen (15) month period after the Release Date of the Upgrade." After that, "each Upgrade family is entitled to receive Troubleshooting only for a subsequent nine (9) months." A third rule applies inside a family: "When an Update is made available, the previous Update within the same Upgrade family shall cease to be Maintained."

The policy uses this release as its own example. It says "the PC 2024.3 Upgrade family will be Maintained until March 31, 2026 and Troubleshooting will be available until December 31, 2026." Those are the same two dates the table gives. Nutanix's data carries December 5, 2024 as the pc.2024.3 release date. Fifteen months of maintenance from that month, then nine months of troubleshooting, give the two months on the table.

The policy defines the words that matter. "Maintained" means Nutanix "will provide Updates that have workarounds and bug fixes for Errors but will not provide Upgrades." End of Maintenance "is the date after which Nutanix will only provide Troubleshooting." Troubleshooting means "workarounds and access to documentation", and "Where possible it may also include the provision of a Patch Release." The policy also says it applies only to customers with an active Support contract.

The Prism Central policy reaches further than Prism Central itself. Nutanix says it "is also generally inclusive of" other software products, and names Self Service, Microservices Platform (MSP), Objects Manager, Files Manager, Flow Virtual Networking (FVN), Flow Networking Security (FNS) and Nutanix Cluster Check (NCC).

Running Nutanix Prism Central past end of life?
Extended support past the official EOL date exists for many products in this position — whether it covers Nutanix Prism Central is exactly what we check. Tell us where to reach you and we’ll reply with matched options and pricing guidance — or an honest “no vendor covers this.” Free, no obligation.

Free · No obligation · Independent — we track the dates, vendors don’t pay for placement · dates verified against vendor sources. See all support options →
If you choose a provider we introduce, we may receive a referral fee from that provider. It never changes a date or a score.

Prism Central releases and their dates

Dates as Nutanix's table gives them, converted to the last day of the month as its notes direct. The status badge follows End of Support Life. Each release links to its live status page here.

ReleaseGA (Nutanix's data)End of MaintenanceEnd of Support LifeStatus
pc.7.6July 27, 2026October 31, 2027July 31, 2028Supported
pc.7.5December 9, 2025September 30, 2027June 30, 2028Supported
pc.7.3June 24, 2025September 30, 2026June 30, 2027Approaching
pc.2024.3December 5, 2024March 31, 2026December 31, 2026Approaching
pc.2024.2September 17, 2024January 31, 2026October 31, 2026EOL

The pc.7.5 dates are six months longer than the fifteen plus nine month rule gives from its release date. Nutanix's table notes cover that case: "For the releases that have had extensions, the dates in the table are inclusive of the extensions". Every Prism Central release back to the 5.x lines is on our Nutanix Prism Central lifecycle page, with the dates re-checked at every build.

Key dates

What ended at End of Maintenance, and what ends next

Nutanix's Software Support Summary table spells out what each phase includes. For software at End of Maintenance, the table no longer marks upgrades and updates, maintenance releases, security patches and bug fixes, new features and enhancements, certification with new third-party or Nutanix products and versions, or new hardware support. What remains is root cause analysis, problem reproduction in Nutanix Support Labs, the response time SLA, support contract renewal, support requests by web and phone, workarounds, and the knowledge base.

That has been the position of pc.2024.3 since March 31, 2026. A team on pc.2024.3 can still open a case and get a workaround. It should not plan on routine fixes. Nutanix's definition of Troubleshooting leaves room for a patch release "where possible", which is not a schedule. Interoperability is the second risk. The table does not include certification with new Nutanix products or versions after End of Maintenance, so do not assume later AOS releases are certified with pc.2024.3.

At End of Support Life, Nutanix's definition is blunt: it "is the last date that the product is entitled to receive applicable Support. After this date, all Support for the product will cease unless entitled by an active Extended Support contract." The summary table leaves only knowledge base access. A footnote names the one software exception: "assistance related to upgrading from your EOSL version to a supported version." The End of Support Life table adds a practical note of its own: "One click download is disabled for versions which have reached End of Support Life".

Prism Central is the management plane for the clusters registered to it. Its support status touches every one of them. That is the reason to treat December 31, 2026 as a platform date and not a single-server date.

How to check what you are running

Nutanix's End of Support Life table groups Prism Central builds into lines. Any Prism Central whose version starts pc.2024.3 is on the Upgrade family whose support ends on December 31, 2026. Every build in that family carries the same two end dates in Nutanix's data. A later build inside pc.2024.3 does not move the date.

We did not read Nutanix's Prism Central guides for this page, so it does not give a click path for finding the version in the interface. For a wider estate, our EOL Checker and API resolve a Prism Central version against the dates above.

Upgrade path to a maintained release

  1. Pick the target by its dates. pc.7.6 is maintained to October 31, 2027, with End of Support Life on July 31, 2028. pc.7.5 is maintained to September 30, 2027, with End of Support Life on June 30, 2028. The two are one month apart, so the choice turns on what your AOS clusters can pair with, not on the calendar.
  2. Treat pc.7.3 as a short stop. Its End of Maintenance date was September 30, 2026 and its End of Support Life is June 30, 2027. Landing there moves you from one troubleshooting-only release to another. Use it only if an upgrade hop requires it.
  3. Check the AOS pairing first. Nutanix's policy says "Each Prism Central Upgrade family will be compatible with the current and previous two (2) active AOS Upgrade families." For exact pairs it points to the Software Interoperability page on the Nutanix Support Portal. AOS has its own clock: AOS 7.0 has the same two dates as pc.2024.3 in our data, End of Maintenance March 31, 2026 and End of Support Life December 31, 2026. Our Nutanix AOS page has every AOS release.
  4. Read the hops at Nutanix. Our data holds dates, not upgrade hops. Nutanix publishes valid hops on the Upgrade Paths page of its support portal. We did not read that page for this guide, so it names no hops. Read it for your exact build before you schedule the work.
  5. Expect the next clock. Nutanix's policy says Prism Central Upgrades are typically made available every six to nine months and Updates every four to six weeks. With fifteen months of maintenance per Upgrade family, staying inside maintenance means an upgrade about once a year.

What to do before December 31, 2026

  1. List every Prism Central instance and its version. Include test and disaster recovery sites. Mark each one that starts pc.2024.3 or pc.2024.2.
  2. List what follows the same policy. Self Service, Microservices Platform, Objects Manager, Files Manager, Flow Virtual Networking, Flow Networking Security and Nutanix Cluster Check are named under the Prism Central policy. Check their versions in the same pass.
  3. Choose pc.7.5 or pc.7.6 and confirm the AOS pairing. Use Nutanix's Software Interoperability page for the registered clusters. If the pairing needs an AOS upgrade as well, plan both and follow the order Nutanix's upgrade documentation gives.
  4. Raise open problems now. Until the date, pc.2024.3 is inside Nutanix's troubleshooting phase. After it, the policy says "Nutanix does not provide support for products that have reached EOSL", with upgrade assistance as the one software exception.
  5. Download what you need before the date. Nutanix's table notes say one click download is disabled for versions that have reached End of Support Life.
  6. Schedule the upgrade with room to spare. Allow time for a prerequisite hop or an AOS upgrade that the first check did not show.

Frequently Asked Questions

When does Nutanix Prism Central pc.2024.3 reach end of life?

Nutanix Prism Central pc.2024.3 reaches End of Support Life on December 31, 2026. Its End of Maintenance date was March 31, 2026. Nutanix's End of Support Life Information table prints each date as a month, and its notes say those months refer to the end of the month.

What ended for pc.2024.3 at End of Maintenance?

Nutanix's Software Support Summary table stops marking upgrades and updates, maintenance releases, security patches and bug fixes, new features, and new certifications for End of Maintenance software. Root cause analysis, problem reproduction in Nutanix's labs, the response time SLA, support requests by web and phone, workarounds and the knowledge base stay. Nutanix defines this phase as Troubleshooting: workarounds and access to documentation, which where possible may also include a patch release.

What happens when pc.2024.3 reaches End of Support Life?

Nutanix defines End of Support Life as the last date a product is entitled to receive applicable support; after it, all support for the product ceases unless an active Extended Support contract applies. Its summary table leaves only knowledge base access for EOSL software, and the policy adds one software exception: help with upgrading from the EOSL version to a supported version. The table's notes add that one click download is disabled for versions that have reached End of Support Life.

Which Prism Central version should I upgrade to?

On Nutanix's table, pc.7.5 and pc.7.6 are the two Prism Central lines inside their maintenance period. pc.7.5 is maintained to September 30, 2027 with End of Support Life on June 30, 2028. pc.7.6 is maintained to October 31, 2027 with End of Support Life on July 31, 2028. pc.7.3 is already past End of Maintenance, so it is a short stop. Nutanix's Upgrade Paths and Software Interoperability pages on its support portal give the hops and the AOS pairings for your cluster.

Why does pc.2024.3 get about two years of support?

Nutanix's Prism Central policy maintains each Upgrade family for fifteen months after its release date, then gives nine months of troubleshooting only. pc.2024.3 was released on December 5, 2024, so both periods were fixed from that month. Nutanix's policy uses PC 2024.3 as its own worked example, with the same two end dates as the table.